UNITED STATES NAVAL ACADEMY
Electrical and Computer Engineering Department

EE 485A: Introduction to Microelectromechanical Systems

Fall 2009-2010

Text: Foundations of MEMS, Chang Liu, Pearson Education, Inc., Prentice Hall, 2006.

Because of the small size of the microfabrication lab, the class will be divided into two groups, and your lab day may be Tuesday or Thursday, or we may work in the lab for a portion of the class period on both days.

WEEK

LECTURE

LAB

ASSIGNMENTS

1

25-Aug

27-Aug

Course Introduction

(pp. 1-43)

Lab 1A-C:   Material Deposition

 

2

1-Sep

3-Sep

Materials: Electrical  and Mechanical Properties

(pp. 48-72)

Lab 1D:  Photolithography

Problem Set 1 due 1 Sep

3

10-Sep

(no class Tues)

Mechanics of Materials: Beam Bending & Spring Constants

(pp. 73-83)

Lab 1E: Etching

Problem Set 2 due 10 Sep

4

15-Sep

17-Sep

Resonance and Pull-In

(pp. 83-116)

Electrostatic sensing and actuation

(pp. 116- 145)

Lab 2: MEMSPro Introduction

Problem Set 3 due 15 Sep

Lab 1 handout due 17 Sep

5

22-Sep

24-Sep

Review (Tuesday)

Exam I: Thurs, 24 September

Lab 2 wrap-up

Problem Set 4 due 22 Sep

6

29-Sep

1-Oct

Thermal Sensing and Actuation

(pp. 153 -200)

Bulk Micromachining Intro

Lab 3: Bulk Micromachining

Lab 2 handout due 29 Sep

 

7

6-Oct

8-Oct

Piezoresistive Sensors

(pp. 207-240)

Lab 3, cont.

Problem Set 5 due 6 Oct

8

13-Oct

15-Oct

 

Piezoelectric Sensing and Actuation

(pp. 245-273)

Lab3, cont.

(pre-lab)

Problem Set 6 due 13 Oct

9

20-Oct

22-Oct

Magnetic Actuation

Comparison of methods

(pp. 279-321)

Surface Micromachining Intro

Lab 4: Use of Standard Processes

Problem Set 7 due 20 Oct

Lab 3 Report due 22 Oct

10

27-Oct

29-Oct

Lab 4, cont.

Lab 4, cont.

Problem Set 8 due 27 Oct

Williams et al., JMEMS 2003

11

3-Nov

5-Nov

Review

Lab 4 wrap-up

Exam II

Thursday 5 Nov

Lab 4 report due 5 Nov

12

10-Nov

12-Nov

Polymer MEMS

(pp. 397-419)

Microfluidics

(pp. 422-448)

Lab 5: Surface Micromachining

No homework

13

17-Nov

19-Nov

Optical MEMS

(pp. 486-502)

RF MEMS

(Switch Review, Tunable RFMEMS Review)

Lab 5, cont.

Problem Set 9 due 17 Nov

14

24- Nov

No lecture

(Thanksgiving Week)

Lab 5, cont.

Problem Set 10 due 24 Nov

15

1-Dec

3-Dec

Final project intro

Lab 5 completion

Lab 5 report due 8 Dec

16

8-Dec

10-Dec

Final project

Final project

BEAT ARMY!


FINAL PROJECT REPORT DUE BY OUR EXAM DATE