Completion Schedule for Remainder of Academic Year

End of Semester, Fall 2004

06JAN05    Renew Engineering Design Work after Holiday Leave

15JAN05    Receive Remaining Components (COM-5101 Board, Power Amplifiers, Low Noise Amplifiers)

01FEB05    Finish Troubleshooting Closed Link Communications

02FEB05    Begin RF Link Communications Test

15FEB05    Complete RF Link Communications Test

16FEB05    Connect ICSat to Command and Data Handling System

15MAR05   Complete Voltage Spike and Current Spike Tests

30MAR05   Begin Construction of Prototype ICSat

15APR05    Complete Construction of Prototype ICSat

30APR05    Complete Thermal Vacuum Test

01MAY05 - 27MAY05    Turnover