Completion Schedule for Remainder of Academic Year
End of Semester, Fall 2004
06JAN05 Renew Engineering Design Work after Holiday Leave
15JAN05 Receive Remaining Components (COM-5101 Board, Power Amplifiers, Low Noise Amplifiers)
01FEB05 Finish Troubleshooting Closed Link Communications
02FEB05 Begin RF Link Communications Test
15FEB05 Complete RF Link Communications Test
16FEB05 Connect ICSat to Command and Data Handling System
15MAR05 Complete Voltage Spike and Current Spike Tests
30MAR05 Begin Construction of Prototype ICSat
15APR05 Complete Construction of Prototype ICSat
30APR05 Complete Thermal Vacuum Test
01MAY05 - 27MAY05 Turnover
';