ICSat Testing Status

 

ICSat testing began in the Summer of 2004 and will continue through the Fall of 2005.  The following tests have been completed:

  1. Closed Communications Link Test
    1. Test Status -- COMPLETE JUL04
    2. All of the ComBlock circuit boards successfully passed data from the receiver and back out through the transmitter. The Command and Data Handling System was not included in this test.
    3. Test Setup and Results
  2. RF Link Test
    1. Test Status -- IN PROGRESS NOV04
    2.  
    3. Test Setup and Results